A portion of this building had experienced
some interior slab settlement. The soil
investigation identified subsurface conditions
that were consistent with sinkhole activity.
CFI installed 24 grout injection points
inside and around the affected portion of
the structure. We injected 339 cubic yards
of grout, installed 80 underpins, and
replaced over 3,000 square feet of structural
slab to overcome the identified subsurface
problems.
|
|
|
|
|
|
|
|
|
|